AUSWIDE PLUMBING ASSIST COMDAIN WITH 9.5KM WATERMAIN PIPELINE

March 15, 2018

Auswide Plumbing have been engaged by Comdain Infrastructure to install 9.5kms of DN 200mm RRJ pipeline from Portarlington to Clifton Springs for a new recycled water main for Barwon Water.

The pipeline was installed by both boring and open cut methods which ran through private properties, crown land and road verges. Auswide performed all poly welding for the pipeline and facilitated all civil works.

Once installation was completed the pipeline was hydro tested and passed without any leaks, which was a job well done by the Auswide team. The final connection was completed with a tie in to the existing Barwon Water pump station.

Water main pump station Recycled water main installation Confined space water main oly welding recycled water mainRecycled water main installation portarlington