AUSWIDE PLUMBING COMPLETE OVER 4.5KM OF WATERMAIN INSTALLATION IN CRAGIEBURN

January 1, 2020

Auswide Plumbing have completed the installation of 4,600m of a non-drinking water main installation on Mickleham Road in Craigieburn.

Works involved welding of 355mm and 400mm HDPE, with new pipework being installed via HDD and open cut.

The work location comprised of a significant amount of flora so several protection zones were established. Pipe installation was completed with minimal disruption to the vegetation in the area.

 